The experience from last three years suggests that the federal and state governments have been effective in stimulating the initial momentum and investments in the solar. Moreover, the growth has been facilitated without disrupting the overall consumer tariffs and by keeping the total subsidy support under manageable levels. This has been mostly achieved by adopting a calibrated approach where the government is developing solar in a phased manner that allows it to continuously modify policies and guidelines based on the performance, experiences and market conditions of the earlier phases. However, the challenge for the government is to further accelerate and up-scale the solar development in the coming years while minimising the constraints imposed by resulting higher consumer tariffs and subsidy requirements.
Thus far, the federal and some state governements have managed to put solar on their political agenda. However, the issues arising mainly from the institutional set-ups, political stability and priorities, general macro-economic conditions and competing demand for subsidies may result in a gap between the strong political rhetoric and the actual implementation. This is discussed in detail in the below section.
- Indian electricity policy is concurrent in nature which places it under control of both federal and state governments. The federal government develops guidelines which have a political agenda and then nudges all state governments to shift towards it. However, the response from states to any nudging varies depending on political factors (closeness of state governments to the federal government) and economic factors (whether the state is rich in resources, net energy importer or exporter etc.). Therefore, since by constitution setting concrete targets and its implementation is a mandate with state governments, solar development across the country may not be uniform.
- Secondly, although JNNSM is declared as one of the climate change mitigation mechanism in National Action Plan on Climate Change (NAPCC), improving electricity access at relatively lower costs is a higher political priority in India. Up-scaling JNNSM is more focussed on tapping into the international funds allocated for climate initiatives rather than allocation of internal resources. Thus, solar doesn’t rank particularly high on the overall political agenda for energy. Political priorities include energy security, increased conventional capacity additions, ramping of domestic fuel (coal and gas) supplies and improved transmission and distribution grids. The fact that there are sufficient cases where higher consumer tariffs have swung elections, or have been perceived to do so, promoting higher levels of relatively expensive solar power in the near term may be difficult.
- Thirdly, the underlying macro-economic conditions in India may somewhat impede the large scale growth of solar in near future. The very high levels of the twin deficits i.e. the Current Account Deficit (CAD) and Fiscal Deficit (FD) has already delayed the announcement of Phase 2 of JNNSM. The FD and CAD have spiked to unsustainable levels of 5.2% and 5.3% of GDP respectively. In its attempt for fiscal consolidation, the federal government has stated its intentions to limit all central subsidies by reducing them to less than 1.75% of GDP by FY16. This implies that the government may spend relatively less by pre-empting subsidies particularly those which may not have any direct bearing on the electoral outcomes.
![]() |
| CAD and FD as percentage of GDP |
- Lastly, the large scale solar development has to compete with the needs of other critical energy infrastructure in the country. In the XI Plan, only about INR 38 billion (0.08%) of the total budget expenditure of INR 52 trillion was allocated to Ministry of New and Renewable Energy (MNRE). In contrast, the budget allocation to Ministry of Petroleum and Natural Gas (MoPNG) and Ministry of Power (MoP) was INR 1,179 billion (2.4%) and INR 341 billion (0.7%) respectively. When compared to investment requirements of MNRE for XI Plan, the budget outlay was grossly inadequate. Similarly, the proposed budget outlay of about INR 67 billion for MNRE in the XII Plan, which is more than double the XI Plan may unlikely meet the requirements of the ambitious targets for the period.
![]() |
| Budget Allocation for different ministries as a percentage of Total Budget Expenditure |
As is evident from the above discussion, whether the ambitious national and state level targets for solar development are implemented successfully remains largely uncertain. Much depends on the federal-state power relations, subsidy support from federal government, availability of international climate funds and willingness or ability of each state to absorb higher electricity prices.